Development efforts for PresNet in 2010 are using the TDL co-cirectors as product owners with the TDL chief technology officer acting as their proxy. User stories have been selected to create a proof of concept system and create domain expertise among the TDL development staff. (See this article for descriptions of common Scrum terms.)
Contents |
Sprints 1-3
- Three three-week sprints beginning March 22, 2010 and concluding by TCDL 2010 (May 17)
- Goal: Package and deliver TDL-managed assets to TACC
- federated ETD collection
- TDL-hosted journals, wikis, blogs, and conferences
- TxLOR assets
- Software platform: iRODS
- Primary partner: Texas Advanced Computing Center (TACC)
- renting 10 terabytes of storage (1 copy disk, 2 copies tape)
Sprint 4
Sprint 4 was a one-week re-factoring spring in which the TDL team reorganized the code base.
Sprint 5 (concluded June 11, 2010)
Completed user stories
The team committed to completion of the following two stories in sprint 5:
- The "TDL federated ETD Collection" story: "As a TDL admin, I want to be able to preserve the TDL federated ETD collection."
- The "Nominate a collection for preservation" story: "As a content collector, I want to nominate a collection for preservation."
Uncommitted backlog story:
The team finished its committed stories early and made substantial progress towards completion of a third story from the backlog:
- The "cost of preservation" story: "As a preservationist, I want to know the effective cost of my collections."
Sprint 5 demo presentation
Presentation slides for sprint 5 demo.
Sprint 6 (concluded August 6, 2010)
For a list of completed user stories for PresNet Sprint 6, go to JIRA Studio.